Project Sequence for the Downtime-Optimized Conversion
Before you execute the downtime-optimized conversion procedure of your SAP ERP system, plan and prepare your project for the
downtime-optimized conversion to SAP S/4HANA by performing several test runs.
Context
The first run is essential to create the Customizing and to determine additional tables to be migrated in uptime.
Procedure
Perform a regular conversion run without downtime-optimized conversion procedure.
Copy your SAP ERP system to a sandbox system.
Perform a regular conversion on the sandbox system without the downtime-optimized conversion procedure.
Define your Customizing settings and perform all SAP Finance-specific IMG steps on your new SAP S/4HANA sandbox system
as described in SAP Note 2332030 .
Your Customizing settings and IMG activities are recorded in Customizing requests that you need to include in your
subsequent conversion runs as a customer buffer file.
At this point of time, analyze which application tables have a long downtime migration time and can be moved to the
uptime with the downtime-optimized conversion procedure. Use the Impact
Analysis to verify that the selection does not contain tables with large change volume (>
2,000,000 changes per day).
Perform a test run with downtime-optimized conversion procedure.
Copy your SAP ERP system to a test system.
Perform one to several runs of downtime-optimized conversion on the test system.
Include your Customizing requests, which you generated on the sandbox system, in the downtime-optimized conversion
procedure with the Customer Transport Integration feature of the Software
Update Manager on your test system. This feature is described in the SUM guide in section 4 Planning Integration of Customer Transports.
Only relevant for source systems not yet on SAP HANA database: Enter the path and name of the file
containing the selected large tables that should additionally be migrated during uptime.
Perform a productive run with downtime-optimized conversion procedure:
Perform now an update with the downtime-optimized conversion procedure on your production system including your Customizing
requests in the downtime-optimized conversion procedure with the Customer Transport Integration feature
of SUM.