Zero Downtime Option for SAP S/4HANA

Additional Steps for ZDO

This section deals with some steps to be considered in addition to the standard update procedure using SUM.

Interpreting the Results of the Impact Analysis

This step is essential and must not be skipped. If you ignore the results, a serious business impact on production can occur if unchecked business-relevant tables are set to read-only For more information, see Impact Analysis at a Glance.

Functional Validation During the Bridge Runtime on a Non-Productive System

We recommend testing all business processes that must be available for daily operation on the bridge subsystem. For this, the source release must be validated again. Compared to standard upgrades, where only the target release is tested, the test effort can increase significantly.

Considering Load Verification

As with the functional validation, it is recommended to trigger a load check in a non-productive system during the time when users are working on the bridge subsystem. From the upgrade tool perspective, there is no requirement to have real users in the system. The load can also be generated with any load generation and test tool.

Testing the Database Replication Setup

Database triggers used by SAP Landscape Transformation (SLT) scenarios require more attention for ZDO. For more information, see SLT Replication Handling.